House kit assembly recommendationsSection 21 of 24

Assembling a porch or veranda

The veranda floor joists are set on a support board 40 × 150 mm, fixed to the grillage with screws 6 × 80 mm, 2 pcs. at a spacing of 1 m (if the joist span is less than 2000 mm). Fix the floor joists themselves with screws 90 mm (4 pcs. per bearing). The veranda floor joists are set on a support timber 80 × 150 mm, fixed to the grillage with screws 6 × 120 mm, 2 pcs. at a spacing of 1 m (if the joist span is greater than 2100 mm). The floor joists themselves are fixed with screws 90 mm (4 pcs. per bearing). The boards for the joists 80 × 150 mm and 80 × 200 mm are fixed together with screws 4,2 × 64 mm in a staggered pattern at a spacing of 150 mm. The joist spacing is taken from the calculation. For the main structural details, see Appendix No. 6. Technical Solutions Album – porches, terraces, balconies and canopies.

Figure 72Figure 73

Posts are installed on the grillage with reinforced angle brackets KPW-4 (105 × 105 × 90 × 2,5 mm). Beams and posts are fixed to each other with reinforced angle brackets KPW-4 (105 × 105 × 90 × 2,5 mm) and screws 6 × 80 mm. At a support, beams are joined along their length with a metal plate 100 × 300 mm and screws 3,5 × 41 mm. A beam may be fixed to another beam with an OBR-R timber support 150 × 150 × 76 × 2 mm and screws 6 × 80 mm.

Figure 74Figure 75

Rafters are fixed to the lower support with reinforced angle brackets KPW-4 (105 × 105 × 90 × 2,5 mm) and screws 3,5 × 41 mm. Blocking between the rafters is fixed with screws 4,2 × 90 mm, 4 pcs. per block. Double rafters are fixed together with screws 4,2 × 64 mm in a staggered pattern at a spacing of 150 mm. The eaves board is fixed to each rafter it crosses with two screws 4,2 × 64 mm. At a support, single rafters are fixed with screws 6 × 120 mm, 3 pcs. per detail, and double rafters are fixed with screws 6 × 160 mm, 3 pcs.

Figure 76Figure 77

Before proceeding to the next stage of construction, the installation of the structure must be inspected in accordance with technical supervision (Appendix No. 1. Technical Supervision of the Construction of a SIP Panel House Using SIPwall Technology).